4/4/2024 Meeting Online Discussion Points
Getting the Couse back in the Pond Quick summary
Tentative Work Party Planned for April 27 & 28 to install sub floats
Cables & Markers remain from when we were dry.
Water Is flowing good right now, we hope for it slow by end of month.
Sub floats are individually marked for correct position to ease install.
Buoys are ready if needed.
Dam Project remains on Schedule with potential for Testing on May 5th.
If all goes well, we may see a full pond after that which will allow us to complete course checkout and ski - keep your Finger crossed.
If not we will wait and see. Dam and Public safety are top priority.
Tournaments are a go for July
We are applying for our annual Permit renewal
We are applying for our annual insurance Renewal